Citrus County CDBG-DR Budget Plan
Citrus County CDBG-DR Budget Plan
PROJECT INFORMATION:
Planned Start Date |
Planned End Date |
Subrecipient Agreement and Accomplishments Summary |
"Estimated Units to be Completed by the“End Date”" |
"Estimated Funds to be Requested by the “End Date”" |
07/01/19 |
07/01/21 |
Advertise Availability of Funds, Schedule Mandatory Contractor and Resident Meetings, Flood Notices and Tribal/Organizational Letters Sent for Public Comment, Resident Application Intake. |
8 |
$1,000,000.00 |
07/01/19 |
12/01/19 |
HUD Broad Environmental Review, Submit Request for Release of Funds and Environmental Clearance for Unspecified Site Survey to DEO, Submit Documentation to Clear Contract Special Conditions |
0 |
$0.00 |
12/01/19 |
03/31/20 |
Intake, Income Qualification, Advertise For and Open Bids, Contractor Selection. |
0 |
$15,000.00 |
04/01/20 |
10/31/20 |
Award and Execute Housing Contracts – Initiate Site Specific Environmental Reviews |
0 |
$15,000.00 |
11/01/20 |
12/31/20 |
Scattered Sites Demo/Elevate/Replace – 2 Units 25% Complete |
0 |
$15,000.00 |
01/01/21 |
01/31/21 |
Scattered sites: Demo/Elevate/Replacement – 2 Units 50% Complete |
2 |
$240,000.00 |
02/01/21 |
03/31/21 |
Scattered Sites: Demo/Elevate/Replacement – 2 Units 75% Complete |
2 |
$240,000.00 |
04/01/21 |
05/30/21 |
Scattered Sites: Demo/Elevate/Replacement – 2 Units 100% Complete. Submit Closeout Package to DEO |
2 |
$240,000.00 |
06/01/21 |
07/01/21 |
Subrecipient Agreement and Accomplishments Summary |
2 |
$235,000.00 |