07/01/19

07/01/21

Advertise Availability of Funds, Schedule Mandatory Contractor and   Resident Meetings, Flood Notices and Tribal/Organizational Letters Sent for   Public Comment, Resident Application Intake.

8

$1,000,000.00

07/01/19

12/01/19

HUD Broad Environmental Review, Submit Request for Release of Funds   and Environmental Clearance for Unspecified Site Survey to DEO, Submit   Documentation to Clear Contract Special Conditions

0

$0.00

12/01/19

03/31/20

Intake, Income Qualification, Advertise For and Open Bids, Contractor   Selection.

0

$15,000.00

04/01/20

10/31/20

Award and Execute Housing Contracts – Initiate Site Specific   Environmental Reviews

0

$15,000.00

11/01/20

12/31/20

Scattered Sites Demo/Elevate/Replace – 2 Units 25% Complete

0

$15,000.00

01/01/21

01/31/21

Scattered sites: Demo/Elevate/Replacement – 2 Units 50% Complete

2

$240,000.00

02/01/21

03/31/21

Scattered Sites: Demo/Elevate/Replacement – 2 Units 75% Complete

2

$240,000.00

04/01/21

05/30/21

Scattered Sites: Demo/Elevate/Replacement – 2 Units 100% Complete.   Submit Closeout Package to DEO

2

$240,000.00

06/01/21

07/01/21

Subrecipient Agreement and Accomplishments Summary

2

$235,000.00